Fusionchart
- Demonstration:
-
Java API: org.zkoss.zkmax.zul.Fusionchart zkmax.fusionchartz.Fusionchart
- ZK Fushionchart has now entered maintenance mode as of Q2, 2014 as the 3rd party library that it’s based on - Fusioncharts free, has moved out of flash and stopped supporting it.
Employment/Purpose
The Fusionchart which integrates the FusionCharts Free with ZK. The technology makes use of Flash to draw charts and enables the user to customize the style of charts such as bar or line colors.
Fusionchart separates the presentation layer from the data, providing the users with a API to supply data in a clean MVC based manner. In addition to updating the data dynamically, it provides a pleasant user experience as the visual display is updated immediately.
Common Attributes
| Name | Description |
|---|---|
| title | Title of chart |
| threeD | Set true to show three dimensional graph(Note: Some types may not support 3D) |
| type | Type of chart |
| fgAlpha | Foreground alpha |
| model | Model of chart |
Supported Model
| Type | Model | 3D | |—|—|—| | bar | CategoryModel | * | | line | CategoryModel, XYModel | X | | pie | PieModel, SingleValueCategoryModel since 6.5.3 | O | | funnel | SingleValueCategoryModel since 6.5.3 | X | | combination | CategoryModel | O | | stacked_bar | CategoryModel | O | | area | CategoryModel | X | | gantt | GanttModel | X |
Note: 3D bar chart of Fusionchart does not support horizontal orientation now. If you want to use horizontal 3D bar chart, please use Chart component.
Example
Bar Chart
2D Bar Chart
Vertical Bar Chart

<zk>
<div apply="demo.BarchartComposer">
<fusionchart id="mychart" title="Bar Chart" type="bar" width="500" height="250" />
</div>
</zk>
public class BarchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
CategoryModel catmodel = new SimpleCategoryModel();
catmodel.setValue("2001", "Q1", new Integer(20));
catmodel.setValue("2001", "Q2", new Integer(35));
catmodel.setValue("2001", "Q3", new Integer(40));
catmodel.setValue("2001", "Q4", new Integer(55));
catmodel.setValue("2002", "Q1", new Integer(40));
catmodel.setValue("2002", "Q2", new Integer(60));
catmodel.setValue("2002", "Q3", new Integer(70));
catmodel.setValue("2002", "Q4", new Integer(90));
mychart.setModel(catmodel);
}
}
Horizontal Bar Chart

<zk>
<div apply="demo.BarchartComposer">
<fusionchart id="mychart" title="Horizontal Bar Chart" type="bar" orient="horizontal" width="500" height="250" />
</div>
</zk>
public class BarchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
CategoryModel catmodel = new SimpleCategoryModel();
catmodel.setValue("2001", "Q1", new Integer(20));
catmodel.setValue("2001", "Q2", new Integer(35));
catmodel.setValue("2001", "Q3", new Integer(40));
catmodel.setValue("2001", "Q4", new Integer(55));
catmodel.setValue("2002", "Q1", new Integer(40));
catmodel.setValue("2002", "Q2", new Integer(60));
catmodel.setValue("2002", "Q3", new Integer(70));
catmodel.setValue("2002", "Q4", new Integer(90));
mychart.setModel(catmodel);
}
}
3D Vertical Bar Chart

<zk>
<div apply="demo.BarchartComposer">
<fusionchart id="mychart" title="3D Bar Chart" type="bar" threeD="true" width="500" height="250" />
</div>
</zk>
public class BarchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
CategoryModel catmodel = new SimpleCategoryModel();
catmodel.setValue("2001", "Q1", new Integer(20));
catmodel.setValue("2001", "Q2", new Integer(35));
catmodel.setValue("2001", "Q3", new Integer(40));
catmodel.setValue("2001", "Q4", new Integer(55));
catmodel.setValue("2002", "Q1", new Integer(40));
catmodel.setValue("2002", "Q2", new Integer(60));
catmodel.setValue("2002", "Q3", new Integer(70));
catmodel.setValue("2002", "Q4", new Integer(90));
mychart.setModel(catmodel);
}
}
Bar Chart Configurations
You could set the color of all categories in the CategoryChartConfig, here’s a sample code for setting first one and second one to different color .
CategoryChartConfig config = new CategoryChartConfig();
config.setAnimation(false); //You could turn off the animation ,which default is enabled.
SeriesPropertiesMap seriesPropertiesMap = config.getSeriesPropertiesMap();
// Use the index to config the chart
// The color value is required to be HEX code without # due to the restriction of Fuscionchart core.
seriesPropertiesMap.createSeriesProperties(0).addProperty("color","AFD8F8");
seriesPropertiesMap.createSeriesProperties(1).addProperty("color","FF8000");
// ==== Or another way , use category name instead of index ==== //
// seriesPropertiesMap.createSeriesProperties("2001").addProperty("color","AFD8F8");
// seriesPropertiesMap.createSeriesProperties("2002").addProperty("color","FF8000");
fusionchart.setChartConfig(config);
The color is changed after we set the config ,here’s the demo image.

Line Chart

<zk>
<div apply="demo.LinechartComposer">
<fusionchart id="mychart" title="Line Chart" type="line" width="500" height="250" />
</div>
</zk>
public class LinechartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
XYModel xymodel = new SimpleXYModel();
xymodel.addValue("2001", new Integer(20), new Integer(120));
xymodel.addValue("2001", new Integer(25), new Integer(120));
xymodel.addValue("2001", new Integer(30), new Integer(125));
xymodel.addValue("2001", new Integer(31), new Integer(130));
xymodel.addValue("2001", new Integer(32), new Integer(132));
xymodel.addValue("2001", new Integer(35), new Integer(133));
xymodel.addValue("2001", new Integer(40), new Integer(135));
xymodel.addValue("2001", new Integer(55), new Integer(136));
xymodel.addValue("2001", new Integer(60), new Integer(137));
xymodel.addValue("2001", new Integer(65), new Integer(138));
xymodel.addValue("2001", new Integer(75), new Integer(135));
xymodel.addValue("2001", new Integer(80), new Integer(160));
xymodel.addValue("2001", new Integer(85), new Integer(160));
xymodel.addValue("2002", new Integer(20), new Integer(0));
xymodel.addValue("2002", new Integer(25), new Integer(0));
xymodel.addValue("2002", new Integer(30), new Integer(120));
xymodel.addValue("2002", new Integer(31), new Integer(135));
xymodel.addValue("2002", new Integer(32), new Integer(140));
xymodel.addValue("2002", new Integer(35), new Integer(120));
xymodel.addValue("2002", new Integer(40), new Integer(135));
xymodel.addValue("2002", new Integer(55), new Integer(135));
xymodel.addValue("2002", new Integer(60), new Integer(140));
xymodel.addValue("2002", new Integer(65), new Integer(140));
xymodel.addValue("2002", new Integer(75), new Integer(140));
xymodel.addValue("2002", new Integer(80), new Integer(160));
xymodel.addValue("2002", new Integer(85), new Integer(160));
xymodel.addValue("2002", new Integer(90), new Integer(160));
mychart.setModel(xymodel);
}
}
Line Chart Configurations
CategoryChartConfig config = new CategoryChartConfig();
config.setAnimation(false); //You could turn off the animation ,which default is enabled.
config.getChartProperties().addProperty("rotateNames", "1");
SeriesPropertiesMap seriesPropertiesMap = config.getSeriesPropertiesMap();
//Create Seriess Properties by index , you could use category name , too
//ex. seriesPropertiesMap.createSeriesProperties("2001")
seriesPropertiesMap.createSeriesProperties(0)
.addProperty("color", "AFD8F8") ; //change color
seriesPropertiesMap.createSeriesProperties(1)
.addProperty("anchorBorderColor", "FF8000") //change series color
.addProperty("lineThickness", "5"); //Change line weight
fusionchart.setChartConfig(config);
Pie Chart
2D Pie Chart

<zk>
<div apply="demo.PiechartComposer">
<fusionchart id="mychart" title="2D Pie Chart" type="pie" width="500" height="250" />
</div>
</zk>
public class PiechartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
PieModel piemodel = new SimplePieModel();
piemodel.setValue("C/C++", new Double(12.5));
piemodel.setValue("Java", new Double(50.2));
piemodel.setValue("VB", new Double(20.5));
piemodel.setValue("PHP", new Double(15.5));
mychart.setModel(piemodel);
}
}
3D Pie Chart

<zk>
<div apply="demo.PiechartComposer">
<fusionchart id="mychart" title="3D Pie Chart" type="pie" threeD="true" width="500" height="250" />
</div>
</zk>
public class PiechartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
PieModel piemodel = new SimplePieModel();
piemodel.setValue("C/C++", new Double(12.5));
piemodel.setValue("Java", new Double(50.2));
piemodel.setValue("VB", new Double(20.5));
piemodel.setValue("PHP", new Double(15.5));
mychart.setModel(piemodel);
}
}
Funnel Chart
since 6.5.3

<zk>
<div apply="demo.FunnelchartComposer ">
<fusionchart id="mychart" width="550" height="400" type="funnel" />
</div>
</zk>
public class FunnelchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
SingleValueCategoryModel model = new SimpleSingleValueCategoryModel();
model.setValue("Step 1", new Double(21.2));
model.setValue("Step 2", new Double(10.2));
model.setValue("Step 3", new Double(40.4));
model.setValue("Step 4", new Double(28.2));
model.setValue("Step 5", new Double(21.2));
model.setValue("Step 6", new Double(10.2));
model.setValue("Step 7", new Double(40.4));
model.setValue("Step 8", new Double(28.2));
mychart.setModel(model);
}
}
Combination Chart
2D Combination Chart

<zk>
<div apply="demo.CombinationchartComposer">
<fusionchart id="mychart" title="2D Combination Charts" type="combination" width="500" height="250" />
</div>
</zk>
public class CombinationchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
CategoryModel catmodel = new SimpleCategoryModel();
catmodel.setValue("Product A", "08/01", new Integer(20));
catmodel.setValue("Product A", "08/02", new Integer(35));
catmodel.setValue("Product A", "08/03", new Integer(40));
catmodel.setValue("Product A", "08/04", new Integer(55));
catmodel.setValue("Product B", "08/01", new Integer(40));
catmodel.setValue("Product B", "08/02", new Integer(60));
catmodel.setValue("Product B", "08/03", new Integer(70));
catmodel.setValue("Product B", "08/04", new Integer(90));
catmodel.setValue("Product C", "08/01", new Integer(90));
catmodel.setValue("Product C", "08/02", new Integer(30));
catmodel.setValue("Product C", "08/03", new Integer(60));
catmodel.setValue("Product C", "08/04", new Integer(10));
CategoryChartConfig config = new CategoryChartConfig();
SeriesPropertiesMap sPropertiesMap = config.getSeriesPropertiesMap();
sPropertiesMap.createSeriesProperties("Product A").addProperty("parentYAxis", "P");
sPropertiesMap.createSeriesProperties("Product B").addProperty("parentYAxis", "S");
sPropertiesMap.createSeriesProperties("Product C").addProperty("parentYAxis", "S");
mychart.setChartConfig(config);
mychart.setModel(catmodel);
}
}
3D Combination Chart

<zk>
<div apply="demo.CombinationchartComposer">
<fusionchart id="mychart" title="3D Combination Charts" type="combination" threeD="true" width="500" height="250" />
</div>
</zk>
public class CombinationchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
CategoryModel catmodel = new SimpleCategoryModel();
catmodel.setValue("Product A", "08/01", new Integer(20));
catmodel.setValue("Product A", "08/02", new Integer(35));
catmodel.setValue("Product A", "08/03", new Integer(40));
catmodel.setValue("Product A", "08/04", new Integer(55));
catmodel.setValue("Product B", "08/01", new Integer(40));
catmodel.setValue("Product B", "08/02", new Integer(60));
catmodel.setValue("Product B", "08/03", new Integer(70));
catmodel.setValue("Product B", "08/04", new Integer(90));
catmodel.setValue("Product C", "08/01", new Integer(90));
catmodel.setValue("Product C", "08/02", new Integer(30));
catmodel.setValue("Product C", "08/03", new Integer(60));
catmodel.setValue("Product C", "08/04", new Integer(10));
CategoryChartConfig config = new CategoryChartConfig();
SeriesPropertiesMap sPropertiesMap = config.getSeriesPropertiesMap();
sPropertiesMap.createSeriesProperties("Product A").addProperty("parentYAxis", "P");
sPropertiesMap.createSeriesProperties("Product B").addProperty("parentYAxis", "S");
sPropertiesMap.createSeriesProperties("Product C").addProperty("parentYAxis", "S");
mychart.setChartConfig(config);
mychart.setModel(catmodel);
}
}
Stacked Chart
2D Stacked Chart

<zk>
<div apply="demo.StackedchartComposer">
<fusionchart id="mychart" title="2D Stacked Charts" type="stacked_bar" width="500" height="250" />
</div>
</zk>
public class StackedchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
CategoryModel catmodel = new SimpleCategoryModel();
catmodel.setValue("2001", "Q1", new Integer(20));
catmodel.setValue("2001", "Q2", new Integer(35));
catmodel.setValue("2001", "Q3", new Integer(40));
catmodel.setValue("2001", "Q4", new Integer(55));
catmodel.setValue("2002", "Q1", new Integer(40));
catmodel.setValue("2002", "Q2", new Integer(60));
catmodel.setValue("2002", "Q3", new Integer(70));
catmodel.setValue("2002", "Q4", new Integer(90));
mychart.setModel(catmodel);
}
}
3D Stacked Chart

<zk>
<div apply="demo.StackedchartComposer">
<fusionchart id="mychart" title="3D Stacked Charts" type="stacked_bar" threeD="true" width="500" height="250" />
</div>
</zk>
public class StackedchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
CategoryModel catmodel = new SimpleCategoryModel();
catmodel.setValue("2001", "Q1", new Integer(20));
catmodel.setValue("2001", "Q2", new Integer(35));
catmodel.setValue("2001", "Q3", new Integer(40));
catmodel.setValue("2001", "Q4", new Integer(55));
catmodel.setValue("2002", "Q1", new Integer(40));
catmodel.setValue("2002", "Q2", new Integer(60));
catmodel.setValue("2002", "Q3", new Integer(70));
catmodel.setValue("2002", "Q4", new Integer(90));
mychart.setModel(catmodel);
}
}
Area Chart

<zk>
<window border="none" apply="demo.AreachartComposer">
<fusionchart id="mychart" title="Area Charts" type="area" width="500" height="250" />
</window>
</zk>
public class AreachartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
CategoryModel catmodel = new SimpleCategoryModel();
catmodel.setValue("2001", "Q1", new Integer(20));
catmodel.setValue("2001", "Q2", new Integer(35));
catmodel.setValue("2001", "Q3", new Integer(40));
catmodel.setValue("2001", "Q4", new Integer(55));
catmodel.setValue("2002", "Q1", new Integer(40));
catmodel.setValue("2002", "Q2", new Integer(60));
catmodel.setValue("2002", "Q3", new Integer(70));
catmodel.setValue("2002", "Q4", new Integer(90));
mychart.setModel(catmodel);
}
}
Gantt Chart

<zk>
<div apply="demo.GanttchartComposer">
<fusionchart id="mychart" title="Gantt Chart" type="gantt" width="500" height="250" />
</div>
</zk>
public class GanttchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Div comp) throws Exception {
super.doAfterCompose(comp);
GanttModel ganttmodel = new GanttModel();
String scheduled = "Scheduled";
String actual = "Actual";
ganttmodel.addValue(scheduled, new GanttTask("Write Proposal", date(2008, 4, 1), date(2008, 4, 5), 0.0));
ganttmodel.addValue(scheduled, new GanttTask("Requirements Analysis", date(2008, 4, 10), date(2008, 5, 5), 0.0));
ganttmodel.addValue(scheduled, new GanttTask("Design Phase", date(2008, 5, 6), date(2008, 5, 30), 0.0));
ganttmodel.addValue(scheduled, new GanttTask("Alpha Implementation", date(2008, 6, 3), date(2008, 7, 31), 0.0));
ganttmodel.addValue(actual, new GanttTask("Write Proposal", date(2008, 4, 1), date(2008, 4, 3), 0.0));
ganttmodel.addValue(actual, new GanttTask("Requirements Analysis", date(2008, 4, 10), date(2008, 5, 15), 0.0));
ganttmodel.addValue(actual, new GanttTask("Design Phase", date(2008, 5, 15), date(2008, 6, 17), 0.0));
ganttmodel.addValue(actual, new GanttTask("Alpha Implementation", date(2008, 7, 1), date(2008, 9, 12), 0.0));
mychart.setModel(ganttmodel);
}
@Listen("onClick = #mychart")
public void show(Event event) {
Map data = (Map) event.getData();
Messagebox.show(data.toString());
}
private Date date(int year, int month, int day) {
final java.util.Calendar calendar = java.util.Calendar.getInstance();
calendar.set(year, month - 1, day);
return calendar.getTime();
}
}
Event Handling
Fusionchart supports mouse clicking event. You can receive information from event object, including clicked series, category, and value.
The following sample will show how to get an event object and display information on a message dialog.
public class FusionchartComposer extends SelectorComposer<Div> {
@Wire
private Fusionchart mychart;
@Override
public void doAfterCompose(Window comp) throws Exception {
super.doAfterCompose(comp);
// omitted...
}
@Listen("onClick = #mychart")
public void show(Event event) {
Map data = (Map) event.getData();
Messagebox.show(data.toString());
}
}
Supported Events
| Name | Event Type |
|---|---|
| onClick | Mouse clicking event. You can get information of clicked area from this event. |
Supported Children
*None
Version History
| Version | Date | Content |
|---|---|---|
| 6.0.1 | April. 2012 | add new component |
| 6.5.3 | June 2013 | add Fusion Funnel chart integration |
| All | April 2014 | entering maintenance mode |